How to write a defensible scope of work

I think a scope of work is defensible when someone who wasn’t on the discovery call could rebuild your number from it. Most scopes I’ve read fail that test, and plenty of mine did too.

That’s not a knock on the people writing them. Custom work starts with a messy brief: a long call, some notes, a document the client wrote for someone else. Somebody senior turns that into deliverables and a number, usually before anything is signed. They do it well enough to win the work. The trouble shows up later.

Where scopes go wrong

Three things keep coming up when I look back at projects that got hard.

The estimate came in light. Usually nobody got the work wrong. Somebody assumed something, the client assumed something else, and neither assumption made it onto the page.

The scope depended on who wrote it. Two senior people at the same shop can scope the same brief and land far apart, because each one carries their own rules in their head.

And the scoping itself was free work. The best people in the company spent hours on it before the client agreed to anything. That’s fine when you win. It adds up when you don’t.

What makes a scope defensible

When I review a scope now, I look at five things.

Scope clarity. Each deliverable has a done condition the client can check. “Build the portal” isn’t a deliverable. “Customers can log in and see their open orders” is.

Assumptions. Every assumption that moves the number is written down, and you can point to the part of the estimate it moves.

Exclusions. Skip the boilerplate list. Name the nearby work this client is most likely to expect, and say it’s out.

Risk. Each risk says what it does to effort or schedule, and how a change gets handled if it happens.

Estimate basis. Effort by deliverable and role, from your own rates and rules, with a range where you still don’t know. If the only thing on the page is a total, nobody can defend it, including you.

Try it on the last scope that turned into a hard project. Score it honestly, on what’s on the page and not what you meant. In my experience the lowest row is where the trouble started. Then score the next one before it goes out.

None of this is new. Most of us know it. We skip it because a blank page and a deadline push you toward the version that wins the work tonight, instead of the one that holds up three months in.

My position

A defensible scope isn’t a longer document. It’s one where the assumptions, the risks and the math are on the page instead of in someone’s head. That makes it easier to defend, and when it’s wrong, you can see where.

I’d go one step further. If your scopes change depending on who wrote them, look for the rules nobody wrote down before you blame anyone’s estimating.

I still scope our custom builds at Hoyack myself, and I’m building a scoping tool around these checks. It’s called Service Orchard. It’s early, and I’m looking for a few design partners.

If you’d rather compare notes on how you scope, book a 15-minute fit call with Brandon.

If you think I’ve got the test wrong, tell me. What would you add to the list?